Payment terms: advance, progress payments and retention

شروط الدفع: الدفعة المقدمة والدفعات المرحلية والمحتجزات

The price wins the job, but the payment terms decide whether you can finish it without borrowing. This guide covers the payment structures contractors in the UAE use and how to write them so there is nothing to argue about.

Updated اقرأ هذا الدليل بالعربية

In short: Most UAE contracting jobs are paid in stages: an advance before work starts, progress payments as stages are completed or monthly, and a final payment at handover, sometimes with a retention held until snags are closed or a defects period ends. Write each stage as a percentage, an AED amount and the event that triggers it.

The three parts of a payment schedule

  • Advance (mobilisation) payment. Paid on signing, before you buy materials or bring a team. It shows the client is committed.
  • Progress payments. Tied to clear events, such as after first fix or after tiling, or paid monthly on longer jobs against work done.
  • Final payment. At handover, once the work is complete.

Retention: what it is and how to handle it

Retention is a part of each payment, or of the final payment, that the client holds back until snags are closed or a defects period ends. It protects the client, but it also delays your money.

  • Agree the percentage and the release date in writing, before you sign.
  • Tie the release to an event you control, such as "snag list closed", not to the client's satisfaction.
  • Track every retention you are owed, with its release date, and invoice it on that date.
  • Check the VAT treatment of retention with your accountant.

A sample payment schedule

A villa renovation of AED 150,000 before VAT.

StageTriggerShareIncl. 5% VAT (AED)
AdvanceOn signing30%47,250
Progress 1First fix complete30%47,250
Progress 2Tiling and joinery complete30%47,250
FinalSnag list closed10%15,750
Total100%AED 157,500
Example figures for layout only, not market prices.

Protect your cash flow

  • Do not start before the advance arrives. Mobilising on a promise is how contractors end up financing the client.
  • Invoice on the trigger, the same day. A late invoice is a late payment.
  • Set a due date on every invoice, for example 7 days.
  • Stop work clause: state that work pauses if a payment is overdue by a set number of days.

General contracting practice in the UAE. Take legal advice on your own contract terms.

Questions contractors ask

أسئلة يطرحها المقاولون

How much advance can a contractor ask for in the UAE?

There is no fixed rule for private jobs; it is agreed in the contract. Contractors commonly ask for enough to cover materials and mobilisation. Write the percentage and amount in the quotation.

When should retention be released?

When the event in your contract happens, for example the snag list is closed or the defects period ends. Write the event and the date in the contract and invoice the retention on that date.

Should payment terms be in the quotation?

Yes. When the client signs the quotation, they agree to the schedule too.