In short: A fit-out BOQ groups the work into sections (preliminaries, demolition, partitions and ceilings, flooring, finishes, joinery, MEP), and lists each item with a description, quantity, unit, rate and amount in AED. It ends with a subtotal, 5% VAT and the total.
The columns every BOQ needs
- Item number, so the client and you can refer to a line (for example 3.2).
- Description, specific enough to price: material, size, finish and what is included (supply, install, or both).
- Quantity and unit: m² for areas, lm for lengths, nos for counted items, lot for a lump sum.
- Rate and amount in AED. Amount = quantity × rate.
Standard sections for a fit-out
- Preliminaries: site setup, protection, permits by the contractor, cleaning, waste removal.
- Demolition and strip-out.
- Partitions and ceilings: gypsum or block walls, false ceilings, access panels.
- Flooring: screed, tiles, vinyl, skirting.
- Wall finishes: paint, wallpaper, cladding, tiling.
- Doors and joinery: doors, frames, ironmongery, cabinets, counters.
- MEP: electrical, lighting, plumbing, HVAC modifications, fire alarm and sprinkler changes.
- Provisional sums and exclusions.
A sample fit-out BOQ in AED
A small office fit-out of about 120 m², shortened to one line per section.
| Item | Qty | Unit | Rate | Amount (AED) |
|---|---|---|---|---|
| 1.1 Preliminaries and site protection | 1 | lot | 6,000 | 6,000 |
| 2.1 Strip out existing finishes | 120 | m² | 35 | 4,200 |
| 3.1 Gypsum partitions, 12.5 mm both sides | 85 | m² | 120 | 10,200 |
| 3.2 False ceiling, gypsum board | 120 | m² | 95 | 11,400 |
| 4.1 Porcelain tiles 60×60 with skirting | 120 | m² | 150 | 18,000 |
| 5.1 Emulsion paint, 3 coats | 340 | m² | 22 | 7,480 |
| 6.1 Doors with frames and ironmongery | 6 | nos | 2,400 | 14,400 |
| 7.1 Lighting and power modifications | 1 | lot | 16,500 | 16,500 |
| Subtotal 88,180 · VAT 4,409 | AED 92,589 |
Tips that save arguments later
- Measure from drawings or site, and say which. If quantities are approximate, write "to be remeasured".
- Use provisional sums for items you cannot price yet, and say how they will be adjusted.
- Keep the item numbers fixed. Variations and progress claims refer back to them.
- List exclusions under the BOQ, not in an email.
Standard measurement practice for UAE fit-out works. Figures are examples only.