In short: Build each unit rate from its direct costs per unit: materials (with wastage), labour (hours × hourly cost) and equipment. Add a share of overheads (office, vehicles, insurance, staff not on site), then your profit margin. Review the rates when material prices or wages change.
The parts of a unit rate
- Materials: quantity per unit × price, plus wastage.
- Labour: hours per unit × the full hourly cost of the worker (salary, visa, housing, transport, insurance).
- Equipment and tools: hire or wear per unit.
- Overheads: a percentage covering costs not tied to one job.
- Profit: your margin on top.
A worked example: porcelain tiling per m²
| Part | Calculation | AED per m² |
|---|---|---|
| Tiles | 1.08 m² × 55 (8% wastage) | 59.40 |
| Adhesive and grout | per m² | 9.00 |
| Labour | 0.6 h × 30 | 18.00 |
| Tools and consumables | per m² | 2.00 |
| Direct cost | 88.40 | |
| Overheads 12% | 88.40 × 12% | 10.61 |
| Profit 15% | 99.01 × 15% | 14.85 |
| Unit rate before VAT | AED 113.86 |
Round to a rate you will use, such as AED 115 per m², and record how you built it.
Keep your rates honest
- Measure real productivity on your own jobs: how many m² a team actually lays in a day.
- Use the full labour cost, not just salary.
- Update when prices move, and date every rate.
- Keep one rate book for the whole company, so every quote uses the same numbers.
Standard estimating practice. Figures are examples only.