Rate analysis: how to calculate your unit rates

تحليل الأسعار: كيف تحسب سعر الوحدة

A unit rate, such as AED per m² of tiling, is the building block of every quote. Contractors who copy rates from competitors or old jobs often lose money without knowing which items cost them. Rate analysis shows exactly what each rate is made of.

Updated اقرأ هذا الدليل بالعربية

In short: Build each unit rate from its direct costs per unit: materials (with wastage), labour (hours × hourly cost) and equipment. Add a share of overheads (office, vehicles, insurance, staff not on site), then your profit margin. Review the rates when material prices or wages change.

The parts of a unit rate

  1. Materials: quantity per unit × price, plus wastage.
  2. Labour: hours per unit × the full hourly cost of the worker (salary, visa, housing, transport, insurance).
  3. Equipment and tools: hire or wear per unit.
  4. Overheads: a percentage covering costs not tied to one job.
  5. Profit: your margin on top.

A worked example: porcelain tiling per m²

PartCalculationAED per m²
Tiles1.08 m² × 55 (8% wastage)59.40
Adhesive and groutper m²9.00
Labour0.6 h × 3018.00
Tools and consumablesper m²2.00
Direct cost88.40
Overheads 12%88.40 × 12%10.61
Profit 15%99.01 × 15%14.85
Unit rate before VATAED 113.86
Example figures for layout only, not market prices.

Round to a rate you will use, such as AED 115 per m², and record how you built it.

Keep your rates honest

  • Measure real productivity on your own jobs: how many m² a team actually lays in a day.
  • Use the full labour cost, not just salary.
  • Update when prices move, and date every rate.
  • Keep one rate book for the whole company, so every quote uses the same numbers.

Standard estimating practice. Figures are examples only.

Questions contractors ask

أسئلة يطرحها المقاولون

What overhead percentage should I use?

Work it out from your own figures: yearly overhead costs divided by yearly direct costs. It differs a lot between companies.

How often should I update my rates?

Whenever material prices or wages change noticeably, and at least once a year.

Should profit be added to overheads?

Most contractors add profit on top of direct cost plus overheads, as in the example. Be consistent across all rates.