In short: Keep quote validity short, base prices on current supplier quotes, buy or reserve key materials when the client signs, use provisional sums for items whose price is uncertain, and on longer jobs agree a price-change clause for named materials. Write all of it in the quotation.
Before you quote
- Get current supplier prices for the big items, with the supplier's own validity date.
- Keep your validity shorter than the supplier's, so you are never holding a price they no longer hold.
- Name brands and specifications, so a substitute is a variation, not your cost.
In the quotation
- Validity: for example 15 days, after which prices are confirmed again.
- Provisional sums: for items the client has not chosen yet, such as sanitary ware, with the allowance stated.
- A price-change clause on longer jobs: named materials are adjusted if their supplier price moves by more than an agreed percentage, with supplier invoices as proof.
After the client signs
- Buy or reserve key materials straight away, using the deposit.
- Track actual costs against your estimate, so you know which rates to update.
What a price rise costs
| At quote | At purchase | |
|---|---|---|
| Cable and accessories | 18,000 | 20,700 |
| Contract price (before VAT) | 120,000 | 120,000 |
| Your margin on the job | 18,000 | 15,300 |
| Margin lost | AED 2,700 (15%) |
General contracting practice. Take legal advice on price-change clauses.