Updated اقرأ هذا الدليل بالعربية
In short: Approvals come in two layers. First the private one: a no-objection certificate (NOC) from the master developer for a villa, or from the building management for an apartment. Then the government one: a permit from the authority that covers the area, such as Dubai Municipality, the Dubai Development Authority or Trakhees in Dubai, or the municipality in Abu Dhabi and Sharjah. Civil Defence and DEWA join when the work touches fire safety, power or water.
Does the job need approval at all?
Painting, replacing fittings like for like and minor repairs usually need only the building or community's permission to work. Anything that changes the structure, the layout, the outside of the building, fire systems, or the electrical or water load usually needs a permit.
- Usually a permit: extensions, removing or adding walls, new openings, changes to the facade, pergolas and outdoor structures, pools, kitchen and bathroom relocations, new electrical load, changes to sprinklers or fire alarms.
- Usually only a work permit or NOC: painting, flooring on existing slabs, like-for-like fittings, joinery that is not fixed to the structure.
Rules differ by community and authority. When in doubt, ask the developer or building management before you quote.
Layer 1: the developer or building NOC
- Villas in master communities (for example Emaar, Nakheel, Damac or Meraas communities) need the master developer's NOC. The developer checks the design against the community's guidelines: setbacks, height, facade and style.
- Apartments and offices need an NOC or permit to work from the building management or landlord. Many buildings also set working hours, deposits and rules for lifts and debris.
- It comes first. The authority usually expects the developer or building NOC before it accepts the permit application.
Layer 2: the government permit
Which authority issues the permit depends on where the property is:
- Dubai Municipality covers most of Dubai. Applications go through its online building permit system.
- Dubai Development Authority (DDA) covers its own zones and runs a fit-out permit service. For some small works the DDA accepts the landlord's or facilities management's permit to work instead.
- Trakhees covers areas under Ports, Customs and Free Zone Corporation.
- Abu Dhabi permits are issued by the municipality through the TAMM platform, with an accredited consultant.
- Sharjah and the other emirates have their own municipality permits. Check with the municipality for the job's location.
Civil Defence and DEWA
- Civil Defence reviews work that touches fire alarms, sprinklers, fire-rated walls or emergency lighting, and a completion certificate may be needed at the end.
- DEWA (or the local utility) approves new electrical load and some plumbing changes. Other emirates have their own utility.
Who does what: contractor, consultant or owner
- The owner signs the applications and pays the developer's and authority's fees, unless the contract says otherwise.
- A licensed consultant or engineer prepares and submits drawings where the authority requires them.
- The contractor often manages the process and must hold the right licence or registration for the work.
Write the split in your quotation: who applies, who pays the fees, and that work starts only after the permits are issued.
Put approvals in your quote and programme
- Price your time, or state that approvals are by the owner.
- Exclude authority and developer fees unless you are including them, and say so.
- Start the programme after approval, not on signing. Approvals can take weeks.
- Keep copies of every NOC and permit on site. Inspectors and building security ask for them.
Dubai Development Authority, Fit-out Permit service (dda.gov.ae); Dubai Municipality building permit procedures (dm.gov.ae); Abu Dhabi Department of Municipalities and Transport, permit news (dmt.gov.ae); Khaleej Times on the Binaa permit platform (2026). Fees, timings and document lists change: confirm with the developer and the authority for each job.