Variation orders: price them and get them signed

أوامر التغيير: سعّرها واحصل على توقيعها

Extra work agreed on the phone is the most common reason contractors lose money at the final invoice. A variation order turns "can you also…" into a priced, signed addition to the contract.

Updated اقرأ هذا الدليل بالعربية

In short: A variation order (also called a change order) records work added, removed or changed after the contract was signed: what changes, the price before VAT, 5% VAT, the effect on time, and the client's signature. Price it and get it signed before you do the work, then add it to the contract value.

When you need a variation

  • The client asks for more: an extra room, a better tile, a new socket.
  • The client removes something: an omission reduces the price, and that is a variation too.
  • Site conditions differ from what you priced, for example damaged pipes behind a wall.
  • Approvals or consultants require changes to the design.

What a variation order includes

  1. A number and date, and a reference to the original quotation.
  2. What changes, with quantities and the item numbers it affects.
  3. The price: before VAT, 5% VAT, and the total.
  4. The time impact: extra days, or none.
  5. The new contract value after the variation.
  6. The client's signature and date, before the work starts.

A sample variation in AED

The client asks to upgrade bathroom tiles and add a niche after the contract is signed.

ChangeQtyUnitRateAmount (AED)
Omit: porcelain tiles 60×60-32m²145-4,640
Add: large-format tiles 120×6032m²2407,680
Add: shower niche with lighting1nos1,3501,350
Before VAT 4,390 · VAT 220AED 4,610
Example figures for layout only, not market prices.

Contract value before: AED 21,861. After this variation: AED 26,471, with two extra working days.

Pricing a variation fairly

  • Use your contract rates for items already in the BOQ.
  • Price new items the same way you priced the original job, including overheads and profit.
  • Include knock-on costs: removing work already done, waste, extra visits.
  • Show omissions as negative lines, so the client sees the full picture.

General contracting practice. For disputes, take legal advice on your contract terms.

Questions contractors ask

أسئلة يطرحها المقاولون

Can I charge for extra work without a signed variation?

You can try, but without a signature it becomes your word against the client's. Get every variation signed before doing the work.

Do variations carry VAT?

Yes. Extra work is charged 5% VAT like the rest of the job.

What if the client wants the work done today?

Send the variation from your phone and get it signed on screen before you start. It takes minutes.